Municipal Building
The copper drainway at a municipal building was leaking into the mayor's office. A new copper drainway was fabricated in sections at the shop and hand soldered on site.
|
1 |
![]() This project involved replacing the copper drainway and installing ice guard under the slate. |
2 |
![]() Scaffolding was erected for the project. |
|
|
3 |
![]() The old copper drainway and slate were removed. |
4 |
![]() The wood deck and drainway were covered with ice guard. |
|
|
5 |
![]() The old drainway liner was taken back to the shop where a new liner was fabricated. |
6 |
![]() To protect the new drainway liner it was put in a trailer and taken to the job. |
|
|
7 |
![]() The new drainway liner was installed. |
8 |
![]() After the drainway was completed the old slate were installed. |
|
|
9 |
![]() The new drainway and ice guard system were soon put to the test. |